Delays by Contractors in Construction of Health Infrastructure and Short Levy of Liquidated Damages in Karnataka

Date of Publication
21-09-2021
Journal Title
Journal ISSN
Volume Title
Publisher
CAG of India
Copyright Holder
Abstract

The Chief Engineer, Health Engineering Wing levied nominal penalty for delays on part of the contractors in completing the works based on the recommendations of the Executive Engineers of the divisions. This resulted in short levy of liquidated damages of ₹ 14.63 crore besides extending undue benefit to the contractors.