Compliance Audit on Cancer Institute in Lucknow

AuthorCAG of India
Date Accessioned2024-06-22T07:01:07Z
Date Available2024-06-22T07:01:07Z
Date of Publication22-09-2022
AbstractThere were significant deficiencies and delays in implementation of the project. The inflated estimates combined with not preparing of the justification statement resulted in excess expenditure of INR 64.60 crore on the project. Construction of Cancer Institute was incomplete (November 2021) even after lapse of more than four years from the scheduled date of completion due to delay on the part of Uttar PRadesh Rajkiya Nirman Nigam and construction agency resulted in denial of full benefits to the intended beneficiaries of the project, viz. cancer patients and research students.
Identifier URIhttps://resourcerepository.azimpremjiuniversity.edu.in/handle/apurr/382
LanguageEnglish
PublisherCAG of India
Series1 of 2022
TitleCompliance Audit on Cancer Institute in Lucknow
Item TypeAudit Report
Files
Original bundle
Now showing 1 - 1 of 1
Loading...
Thumbnail Image
Name:
Compliance Audit on Cancer Institute in Lucknow.pdf
Size:
30.97 MB
Format:
Adobe Portable Document Format
License bundle
Now showing 1 - 1 of 1
No Thumbnail Available
Name:
license.txt
Size:
1.62 KB
Format:
Item-specific license agreed to upon submission
Description: