CAG of India2024-07-282024-07-2830-06-2015https://resourcerepository.azimpremjiuniversity.edu.in/handle/apurr/604The project was assigned by Directorate of Education (DoE) to Delhi State Industrial and Infrastructure Development Corporation (DSIIDC) without any formal Agreement and detailed scope of work in the absence of which DoE could not ensure that DSIIDC carried out all the work envisaged under the project. Effective monitoring mechanism was absent. Out of 183 schools where works were claimed as completed by DSIIDC, DoE found only 78 completed, 50 under progress, and 55 yet to be verified by Principals of schools. DoE released ₹ 343.13 crore to DSIIDC although the Cabinet approved only ₹ 272.94 crore for the project.EnglishCompliance Audit on Integrated Infrastructure Improvement of Govt Schools in DelhiAudit Report